Admin Request for Inspection REA Solar Mini Grid
| Application for | REA Solar Mini-Grid Project |
|---|---|
| REA Code | REA-CAP-MG |
| REA LOT Number | STC050 |
| Blank | Abuja |
| Register as | Corporate |
| NEMSA Certificate Number | 32333 |
| First Name | Folu |
| Last Name | Alabi |
| Position | Vice President, Operations |
| Phone | 08060928305 |
| falabi@ashipaelectric.com | |
| Address |
9 Jalingo Street, Garki Area 2, Abuja. |
| State | Federal Capital Territory |
| Company Name | ASHIPA ELECTRIC LIMITED |
| Company Email | info@ashipaelectric.com |
| Company Phone | 08052305067 |
| Tax Registration Number | 19193765-0001 |
| Address |
9 Jalingo Street, Garki Area 2, Abuja. |
| State | Federal Capital Territory |
| Name of the Village/Community | Kaida-Tsoho Community |
| State | Federal Capital Territory |
| Local Government Area | Gwagwalada |
| Number of Inhabitants | 1200 |
| GPS Coordinates | 9°2’23″N, 6°56’36″E |
| Site Address/Detail Description |
Kaida Tsoho is an off-grid community located around Gwagwalada area Abuja. The community is majorly an agrarian community consisting of 3 main tribes. |
| Activities | Business Activity, Educational Facility, Health Care Facility, Residential |
| Total Solar PV Installed (kWp) | 100 |
| Total Solar PV Energy Produce Per Day (kwh) | 350 |
| Total Storage Capacity (kwh) | 200 |
| Total Load/Energy Requirement (kWh) | 220 |
| Storage Technology/Manufacturer | Lithium Ion / Felicity Solar |
| Type of Coupling (AC/DC) | DC |
| Generator Rated Power (kVA) | 100 |
| Year of Construction | 2022 |
| Fuel Type | Diesel |
| Generator Model/Manufacturer | Perkins |
| Operation | Automatic |
| Date of Installation of Mini-Grid | December 12, 2022 |
| Date of Application | December 29, 2022 |
| Mini-Grid Owner (Full Name) | Ashipa Electric Limited |
| Phone | 08052305067 |
| info@ashipaelectric.com | |
| Manufacturer | Jinko Solar |
| Model | JKM – 550W |
| Technology | Monocrystalline |
| STC power (Wp) | 550 |
| Number of Cells | 144 |
| MPPT Current | 13.07 |
| MPPT Voltage | 40.56 |
| Manufacturer | Jinko Solar |
| Model | JKM – 560W |
| Technology | Monocrystalline |
| STC power (Wp) | 560 |
| Number of Cells | 156 |
| MPPT Current | 12.64 |
| MPPT Voltage | 44.31 |
| Module catalogue # | 560W |
| Number Series | Parallel | 3 Series | 3 Parallel |
| Total Power (Wp) | 5040 |
| Fuse (A) | 63 |
| Surge Protection Device | Type 2 |
| Converter Catalogue | 195v, 120A |
| Cable cross-section | 16sq.mm |
| Module catalogue # | 550W |
| Number Series | Parallel | 3 Series | 3 Parallel |
| Total Power (Wp) | 4950 |
| Fuse (A) | 63 |
| Surge Protection Device | Type 2 |
| Converter Catalogue | 195v, 120 |
| Cable cross-section | 16sq.mm |
| Manufacturer | Felicity Solar |
| Model | SSCM12048 |
| Technology | MPPT |
| Rated Power | 6600W |
| Rated Voltage | 195V |
| Rated Current | 120A |
| Manufacturer | Felicity Solar |
| Model | LBPF-M |
| Technology | Lithium Ion |
| Cell Voltage (V) | 3.6v |
| Battery Voltage | 51.2v |
| C10 Capacity | 10kWh |
| Charge Voltage | 48v |
| Module Catalogue # | 1 |
| Number Series | Parallel | 5 in parallel |
| Total C10 capacity [kWh] | 50 |
| Fuse rating [A] | 250 |
| Date of cell production | December 1, 2020 |
| Cable cross-section [mm²] | 50 |
| Module Catalogue # | 2 |
| Number Series | Parallel | 5 in parallel |
| Total C10 capacity [kWh] | 50 |
| Fuse rating [A] | 250 |
| Date of cell production | December 1, 2020 |
| Cable cross-section [mm²] | 50 |
| Module Catalogue # | 3 |
| Number Series | Parallel | 5 in parallel |
| Total C10 capacity [kWh] | 50 |
| Fuse rating [A] | 250 |
| Date of cell production | December 1, 2020 |
| Cable cross-section [mm²] | 50 |
| Module Catalogue # | 4 |
| Number Series | Parallel | 6 in parallel |
| Total C10 capacity [kWh] | 60 |
| Fuse rating [A] | 250 |
| Date of cell production | December 1, 2020 |
| Cable cross-section [mm²] | 50 |
| PV Generator | Expected open circuit voltage [V] |
| String Number | 1 |
| Value | 158.3v |
| PV Generator | Measured open circuit voltage [V] |
| String Number | 1 |
| Value | 132,8v |
| PV Generator | Expected load circuit voltage [V] |
| String Number | 1 |
| Value | 132.93v |
| PV Generator | Measured load circuit voltage [V] |
| String Number | 1 |
| Value | 121.9v |
| PV Generator | Expected short circuit current [A] |
| String Number | 1 |
| Value | 31A |
| PV Generator | Measured continuity to main equipotential bar [Ohm] |
| String Number | 1 |
| Value | 5 |
| PV Generator | Measured earth resistance of support structure [Ohm] |
| String Number | 1 |
| Value | 3 |
| Inverter/Charge Controller | General visual inspection observations |
| String Number | 1 |
| Reference | All fine |
| Inverter/Charge Controller | Inverter protection settings programmed to local requirements? |
| String Number | 1 |
| Reference | Yes |
| Inverter/Charge Controller | Means of isolating the inverter been provided on the AC side? |
| String Number | 1 |
| Reference | Yes |
| Inverter/Charge Controller | Isolating and switching devices been connected such that PC installation is wired to the “load” side and the public supply to the “source” side? |
| String Number | 1 |
| Reference | Yes |
| Inverter/Charge Controller | All Inverters/Charge controller operating correctly? |
| String Number | 1 |
| Reference | Yes |
| Inverter/Charge Controller | Inverter/charge controller protection settings and installer details displayed on site? |
| String Number | 1 |
| Reference | Yes |
| Battery Storage | Wiring properly done without visual deficits |
| String Number | 1 |
| Reference | Yes |
| Battery Storage | Tightening torque of all screws to connectors to the batteries and in between the cells of the batteries is according to the equipment manufacturer’s recommendations |
| String Number | 1 |
| Reference | Yes |
| Battery Storage | Battery inverter or charge controller parameters are properly set (correct system configuration, date and time, control of the load shedding relays, reading of external temperature sensor verified, …) |
| String Number | 1 |
| Reference | Yes |
| Battery Storage | Deep discharge protection, over-charge protection and temperature monitoring installed and functional |
| String Number | 1 |
| Reference | Yes |
| General Safety/Security | Inverter protection settings programmed to local requirements? |
| String Number | 1 |
| Reference | Yes |
| Official Letter of Request | https://nemsa.gov.ng/wp-content/uploads/formidable/67/Request-for-NEMSA-Site-Inspection.pdf |
| PV System | https://nemsa.gov.ng/wp-content/uploads/formidable/67/Single-Line-Diagram.pdf |
| Charge Controller or Grid-tie Inverter | https://nemsa.gov.ng/wp-content/uploads/formidable/67/Felicity-10kVA-Inverter-Catalogue.pdf |
| Combiner Boxes | https://nemsa.gov.ng/wp-content/uploads/formidable/67/60kW-Wiring-Diagram.pdf |
| Battery System | https://nemsa.gov.ng/wp-content/uploads/formidable/67/Felicity-10kWh-Battery-Catalogue-2.pdf |
| Earthing & Surge Protection System | https://nemsa.gov.ng/wp-content/uploads/formidable/67/Earth-Grid-Diagram.pdf |
| User ID | Dipo Owolabi |